Ongoing / Recently Completed
Foundation wall forming is ongoing; rebar inspection scheduled for July 1, 2026.
Masonry work is complete on the replacement of the gymnasium glass block windows with split-face block.
Demolition of block walls and removal of sand beneath the stage are underway.
Exterior metal siding preparation continues, including the installation of plywood over the existing EIFS.
Installation of two new boilers is ongoing.
Carpenters are reframing exterior openings for new ventilation louvers.
Underground plumbing inspection was completed and passed on June 25, 2026.
Structural steel for the addition was delivered on June 22, 2026.
Looking Ahead
Completion of stage demolition and removal.
Backfilling of interior slab areas and replacement of concrete flooring.
Carpenters will begin metal stud framing for restroom walls.
Installation of new metal door frames for classroom entrances.
Shoring and demolition of masonry wall openings.
Masons will begin concrete block infill work at the stage area.
Excavation and installation of storm drainage systems.
Foundation wall inspection and concrete pour scheduled for July 1, 2026.
Respectfully Submitted, Nate Sheridan, Site Superintendent