Ongoing / Recently Completed

  • Foundation wall forming is ongoing; rebar inspection scheduled for July 1, 2026.

  • Masonry work is complete on the replacement of the gymnasium glass block windows with split-face block.

  • Demolition of block walls and removal of sand beneath the stage are underway.

  • Exterior metal siding preparation continues, including the installation of plywood over the existing EIFS.

  • Installation of two new boilers is ongoing.

  • Carpenters are reframing exterior openings for new ventilation louvers.

  • Underground plumbing inspection was completed and passed on June 25, 2026.

  • Structural steel for the addition was delivered on June 22, 2026.

Looking Ahead

  • Completion of stage demolition and removal.

  • Backfilling of interior slab areas and replacement of concrete flooring.

  • Carpenters will begin metal stud framing for restroom walls.

  • Installation of new metal door frames for classroom entrances.

  • Shoring and demolition of masonry wall openings.

  • Masons will begin concrete block infill work at the stage area.

  • Excavation and installation of storm drainage systems.

  • Foundation wall inspection and concrete pour scheduled for July 1, 2026.

Respectfully Submitted, Nate Sheridan, Site Superintendent